Results in 2019

3,840 MW

installed power capacity

19.3 TWh

power generation

Ust-Ilmisk is the third dam on the Angara River hydroelectric plant cascade. Construction of the dam began in 1963, its reservoir commenced filling in 1974, and its power plant was commissioned in 1980.

The main dam is 1,475 m long and 105 m high. The power plant houses 16 turbines, each generating 240 MW.